Sunday, September 7, 2008

Construction Continues on Pfingsten

Johnson Paving, the company contracted by Cook County to complete work on Pfingsten has remained in contact with GBS regarding its continued work. The rough course in front of GBS will be completed Monday or Tuesday of this week between 9:00 a.m. and 2:00 p.m. They will then raise drains along Pfingsten and hope to put a final course down by the end of this week.

Please continue to give yourself plenty of time to enter school during this construction. Though they have worked well with GBS and are avoiding our most busy times, there will certainly be some disruption to traffic along Pfingsten.

We thank Johnson's Paving for continuing to keep us informed and for working to minimize the impact on our families during this badly needed roadwork.